The 6th of October was an exciting day on site, with partial lock up of the Early Learning Centre completed and the Pizza Oven being fired up for the first time to celebrate.


Partial lock-up means that exterior entrances to the building are now sealed, with interior work continuing as we move closer to opening for Term 1, 2017.


Internally, new features of the building also continue to appear every week.


In the communal centre areas of the Early Learning Centre, plywood feature seats break out from the walls. These will be upholstered as internal finishes are completed.


The first coats of painting have also commenced, including external ceilings, skylights and some classroom walls in the Early Learning Centre.


Meanwhile, external finishes are still underway at the Primary School building, with the aggregate footpaths around the building now poured, allowing for external cladding to commence shortly.

The Primary School Building is also progressing towards lock-up.

SCEA’s Buildings, Grounds and Maintenance Manager, Willem Joubert, was onsite for the partial-lock up on Thursday and joined Davide Maltese, Construction Manager in testing out the ELC’s Pizza Oven!


We invite you to join us for an informal event next Friday, October 14, to join parents, friends, future students and the Northshore team for pizza at the Early Learning Centre building.